試卷名稱
考試中心《》在線考試
試卷年份2011年上半年
試題題型【單選題】
試題內(nèi)容

The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that (  ).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date