色综合成人,苹果电影完整版在线观看未删减港,推拿电影未删减完整版在线观看,成人男女视频网站,特洛伊战争电影完整版未删减 ,91九色丨porny丨交换,无间电视剧在线观看免费完整版

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A seller is awarded a contract to build a pipeline. The contract terms and conditions require that a work plan be issued for the buyer's approval prior to commencing work, but the seller fails to provide one. Which of the following is the BEST thing for the buyer's project manager to do?
A、File a letter of intent.
B、Develop the work plan and issue it to the seller to move things along.
C、Issue a default letter.
D、Issue a stop work order to the seller until a work plan is prepared.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容