色综合成人,苹果电影完整版在线观看未删减港,推拿电影未删减完整版在线观看,成人男女视频网站,特洛伊战争电影完整版未删减 ,91九色丨porny丨交换,无间电视剧在线观看免费完整版

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(6)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(6)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A customer asks the project manager add three small requirements to the project. The project manager believes these small requirements could be done as part of the current baseline plan and would not impact project resources, cost and time lines. The project manager should do which of the following?
A、Include these new requirement and continue to deliver them.
B、Document the request and have the project team analyze it.
C、Ask for more time or money from the customer just in case.
D、Accept the new requirements and inform all stakeholders of the change


相關(guān)試題



更多試題

推薦文章